1) MAY BE REQUIRED. Erosion and sedimentation control plans may be required by the Plan Commission before authorization of construction or installation of improvements showing those structures required to retard the rate of runoff water and those grading and excavating practices that will prevent erosion and sedimentation. Such plans shall generally follow the guidelines and standards set forth in the publication, plans Minimizing Erosion in Urbanizing Areas, as prepared by the U.S. Department of Agriculture, Soil Conservation service, 1972, and the standards contained in this Chapter.#
2) STANDARD FOR EROSION AND SEDIMENT CONTROL FOR LAND-DISTURBING ACTIVITIES. If required by the Plan Commission, plans will not be approved nor permits issued unless erosion and sedimentation leaving the site during and after the land disturbance will not exceed that which would have been eroded if the land had been left in its undisturbed state and/or are controlled in accordance with established procedures, including, but not limited to, Minimizing Erosion in Urbanizing Areas or other technical guidelines as developed by the U.S. Department of Agriculture, Soil Conservation Service.#
3) STANDARDS FOR ON-SITE DETENTION AND RUNOFF CONTROL FOR LAND-DISTURBING ACTIVITIES. Activities subject to on-site detention and runoff control regulation under this Section shall comply with the following standards:#
a. The peak runoff rate after the proposed activities should not be greater than the peak rate which would have resulted from the same ten (10) year storm event occurring over the site with the land in its natural undeveloped state.#
b. Where on-site detention is used for runoff control, the detention facilities shall safely contain and/or safely pass the runoff of a one hundred (100) year storm of any duration.#
c. Determination of on-site detention volumes shall be computed by established procedures equivalent to and calibrated against that procedure promulgated by the United States Soil Conservation Service in its National Engineering Handbook or the technical publication entities “Urban Hydrology for Small watersheds, TR-55,” and accepted by the Village Engineer.#
4) STANDARD FOR TRACKING. For plan approval there must be adequate provisions to prevent the tracking or dropping of dirt or other materials from the site onto any public or private street.#
5) DESIGN CRITERIA, ENGINEERING STANDARD AND GENERAL PRINCIPLES. The person engaged in land-disturbing activities may employ structural or non-structural measures necessary to achieve all applicable standards set out in this Chapter. However, these measures will be evaluated to determine that they follow currently accepted design criteria and engineering standards. The following general principles shall be used when evaluating control plans and granting permits under this Section:#
a. The smallest area of land shall be exposed for the shortest period at any given time during development.#
b. The rough grading of the lot shall include backfilling the basement and all excess earth shall be hauled off the lot.#
c. Accommodation of the increased runoff caused by changes soil and surface conditions during and after development.#
d. Permanent, final plant covering, or structures shall be installed prior to final acceptance.#
e. The plan of development shall relate to the topography and soils of the site so that the lowest potential for erosion is created.#
f. Natural plant covering shall be retained and protected and shall be deemed a dominating factor in developing the site and temporary vegetation, mulching or other cover shall be used to protect the area exposed during the land-disturbing activity.#
6) CONTENTS OF THE CONTROL PLAN. The control plan that may be required by this Section shall contain such information needed to determine soil erosion, sedimentation and runoff control:#
a. A map of the site location showing the location of the predominant soil types.#
b. A topographic map of the site location, including the contiguous properties, existing drainage patterns and watercourse affected by the proposed development of the site and the existing vegetative cover.#
c. A plan of the site showing:#
(1) Name, address and telephone number of the occupant and party responsible for maintaining erosion control.#
(2) Limits of natural floodplain(s) based on a one hundred (100) year flood, if any.#
(3) A timing schedule indicating the anticipated starting and completion dates of the development sequence.#
(4) Proposed topography of the site location with a maximum of two-foot contour intervals showing:#
a) Location of activity, disturbance of protective cover, any additional structure on the site, areas to be seeded or mulched, areas to be vegetatively stabilized and areas to be left undisturbed.#
b) Elevations, dimensions, location of all activities including where topsoil will be stockpiled.#
c) The finished grade, stated in feet horizontal to feet vertical, of cut and fill slopes.#
d) Kinds of utilities and areas of installation, including special erosion control practices for utility installation.#
e) Paved and covered areas in square feet or to scale on a plan map.#
f) Makeup of surface soil (upper six [6] inches) on areas not covered by buildings, structures, or pavement.#
g) Kind of cover on areas not covered by buildings, structures, or pavement.#
7) REVIEW OF PLAN.#
a. The Plan Commission shall review all required control plans within thirty (30) days to determine if the measures are adequate to meet all applicable standards as set out in this Section. The control plan will be approved, disapproved, modified or have additional information required, in writing.#
b. In the event that the plan is disapproved, the applicant may resubmit a new control plan or may appeal the Commission’s decision to the Village Board.#
8) APPEALS.#
a. The Village Board shall hear and decide appeals where it is alleged that there is error in any order, requirement, decision or determination made by the Plan Commission in administering this Section.#
(1) The Village Board may authorize upon appeal in specific cases such variances from the terms of this Section as will not be contrary to the public interest, where owing to special conditions a literal enforcement of the provisions of this Section will result in unnecessary hardship, so that the spirit of this Section shall be observed, public safety and welfare secured, and substantial justice done.#
(2) Such variance may be granted to two (2) or more property owners, including governmental agencies who submit one runoff control plan for two (2) or more parcels of land. In the event it is in the interest of the Village to participate with another property owner(s) shall reimburse the Village an amount equal to the value of the Village lands used but not less than the fair market value of unimproved lands plus the estimated construction cost of the detention capacity that would have been required of the other participant(s) to serve their lands in order to comply with this Section.#