1) Before final plat or a certified survey map approval of any subdivision or minor subdivision within the Village is granted, the subdivider shall either install the improvements required by this Chapter or shall furnish the Village Clerk-Treasurer with a satisfactory surety performance bond or other form of satisfactory surety to the Village to cover the sub divider’s cost of such required improvements as estimated by the Village. Such surety shall provide for one hundred ten (110%) percent of the cost of the required improvements. The purpose of said surety is to secure the actual construction and installation of such improvements immediately after final plat approval or at a time in accordance with the Village Board.#
2) If a surety performance bond is furnished as provided in Subsection (a) above, all required improvements must be completed within one (1) year from approval of the final plat. If not so completed and unless good cause can be shown for granting an extension of time, the Village Board, at its option, may cause all the uncompleted work to be constructed, and the parties executing the bond shall be firmly bound for the payment of all necessary costs thereof. The Village Clerk-Treasurer shall return the bond to the subdivider upon the completion and acceptance of required improvements, at which time a one (1) year maintenance guarantee bond must be filed guaranteeing the timely repair of any defects that may occur in the ensuing year.#
3) Prior to commencing construction of any improvements, the subdivider shall furnish the Village all plans, specifications, and other data and information deemed necessary to determine the character of such proposed improvements. Such plans and specifications shall be examined by the Village and shall be approved if in accordance with the requirements of this Subdivision Ordinance. If the Village determines that their engineering representatives should review the plans and specifications, the subdivider shall be responsible for one hundred (100%) percent of the cost associated with this engineering review.#
4) All requirements hereunder shall be deemed conditions of approval under this Section.#
5) All construction hereunder shall be subject to inspection and approval of the engineering representative of the Village.#
6) The subdivider and Village shall enter into a Development Agreement specifying the improvements to be made in the subdivision, estimates of the cost of such improvements and arrangements for the payment of these costs. Such agreement shall be signed by both the subdivider and Village prior to commencement of any improvements to the land unless otherwise authorized by the Village Board.#
A reading copy of the adopted code, from page 14 of the official chapter PDF. The PDF is the legal text.