1) SANITARY SEWERS.#
a. A public sanitary sewer system adequate to serve the subdivision and compatible with the Village-wide sanitary sewer development plan shall be provided and include a lateral connection for each lot and a satisfactory connection to the Village sanitary sewer system. Each lateral shall be marked in the field by a five (5) foot Douglas fir stake four inches by four inches (4” X 4”) visible above the ground. The subdivider shall pay for one hundred (100%) percent of the costs necessary to install these improvements.#
b. If a sewage lift station is necessary to serve the subdivision, the subdivider shall share in the cost of the lift station and associated force main in the sane ratio that the land area of the subdivision bears to the total area served by the lift station. The subdivider shall pay one hundred (100%) percent of the total construction cost of the lift station and force main up front. The Village will reimburse the subdivider for special assessments which are levied and immediately paid by affected property owners. In the event that special assessments are deferred or paid over a five (5) year period, the subdivider will be reimbursed when the special assessments are paid or when installment payments are received.#
c. If it is necessary to traverse unimproved land with sanitary sewer to serve the proposed subdivision, the Village may authorize installation of such sanitary main and the subdivider shall pay one hundred (100%) percent of the cost of such construction up front. The Village will reimburse the subdivider for special assessments which are levied and immediately paid by benefited property owners. In the event that special assessments are deferred or paid over a five (5) year period, the subdivider will be reimbursed when the special assessments are paid or when installment payments are received.#
d. The Village may authorize the subdivider to construct the necessary sanitary sewer facilities provided that the subdivider enters into a development agreement with the Village agreeing to pay one hundred (100%) percent of the cost of such sanitary sewer facilities. In the event that such construction benefits land outside of the subdivision, authorization will be granted only if the appropriate waives in writing any and all rights to reimbursement from the Village and agrees to pay for one hundred (100%) percent of the cost of such sanitary sewer.#
e. All proposed sanitary sewer extensions require a review by the Portage County Planning Department to check conformance with the Stevens Point Urban Area Sewer Service Plan. Wisconsin Department of Natural Resources approval of all sanitary sewer design pals is also required prior to extending of any sewer lines.#
2) WATER MAIN.#
a. A public water main extension adequate to serve the subdivision and compatible with the Village-wide water system shall be provided and include a lateral connection for each lot and a satisfactory connection to the Village water system. Each lateral shall be marked in the field by a five (5) foot Douglas fir stake four inches by four (4” X 4”) inches, visible above the ground. The subdivider shall pay for one hundred (100%) percent of the costs necessary to install these improvements.#
b. The same provisions for water main shall apply as applicable to sanitary sewer in Subsections (a) (3) and#
(4) above.#
3) OTHER UTILITIES. The subdivider shall cause gas, electrical power, streetlights, and cable facilities to be installed in such a manner as to make service available to each lot. All such utilities shall be installed underground within the boundaries of the subdivision. The subdivider shall have written statements from all the utilities stating that the easements as shown on the final plat are acceptable to them. The subdivider shall pay for one hundred (100%) percent of the costs necessary to install these utilities.#
4) STORM SEWER. Storm sewer facilities where required by the Village Board shall be constructed within the subdivider boundaries in the locations and sizes needed to accommodate the design flow volumes. Such facilities shall include mains, channels, inlets, catch basins, dry wells, and laterals are required. The subdivider shall pay one hundred (100%) percent of the cost of such construction up front. The Village will reimburse the subdivider for special assessments which are levied and immediately paid by benefited property owners. In the event that special assessments are paid by benefited property owners. In the event that special assessments are deferred or paid over a five (5) year period, the subdivider will be reimbursed when the special assessments are paid or when installment payments are received.#
5) EASEMENTS. Easements across lots or centered on rear or side lot lines shall be provided for the installation of utilities when necessary and shall be at least ten (10) feet wide and such easements shall be continuous from block to block. When an easement is centered on a rear or side lot line, the width of the easement in each lot can be added together to meet the width requirements.#